Overall Status Phase 2 :

1. Building 2A Piling Work 80%

2. 1st Floor Building 2A Structural Work 40%

3. 5th , 6th , 7th Floor Building 2B Structural Work 100%

4. Building 2C Piling Work 100%

5. 1st Floor Building 2C Structural Work 50%